March 20, 2007
Time to kick this in gear. Insulation guys come tomorrow.


I finished up all the pre-insulation work. Wiring, covers, studs to hook drywall to, etc... Cleaned the whole place up for them.



Final pictures.

And, at 7am the guys (2 of them showed up). By 9am, they were gone and this whole place was done.









Drywallers tomorrow..... Except, it's supposed to rain... and if it does, they won't come because they won't want to haul the drywall inside with it getting wet. And, we don't want them tracking in the front door with wet shoes.